Feb. 20, 2014 – Blasting to prepare for the East End Crossing is scheduled to occur in Indiana, just east of Utica, between the Ohio River and Salem Road during the week of February 24. There will NOT be any traffic stops for this blast.

The dates and approximate times (within 15 minutes) will be:

  • Tuesday, February 25, at about 4 p.m.
  • Wednesday, February 26, at about 4 p.m.
  • Thursday, February 27, at about 4 p.m.
  • Friday, February 28, at about 4 p.m.

In the event of unfavorable weather or other unforeseen activities, blast times do occasionally change. When changes do occur, they will be posted on www.kyinbridges.com, on Twitter @eastendcrossing and at www.facebook.com/ohiorivereastendcrossing.